Operations
Action Item |
DATE: | Tuesday, October 17, 2017 |
TO: | School Board Members |
FROM: | Jeff Eakins, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve the Projected 2017-18 PECO and Millage Projects | |
EXECUTIVE SUMMARY | |
In 2016 the Florida Legislature appropriated funds to support Public Education Capital Outlay (PECO). The District received an allocation of $4,894,472 for the 2016-17 fiscal year. The district staff is projecting an allocation of $3,436,612 for 2017-18 PECO funds.
Millage funds are received from local property tax assessments. Millage funds also provide payment for debt service, site and bus purchases, and other obligations. The 2017-18 projects identified on the attached sheets are the result of prioritizing recommendations from facility assessments, maintenance staff, Area Superintendents and individual schools. The total millage funds are projected as $135,631,170. |
|
STRATEGIC OBJECTIVES | |
• Engage and communicate with families and stakeholders • Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
The 2017-18 District Capital Outlay PECO Maintenance Fund allocation is projected to be $3,436,612. The 2017-18 Local Millage Assessment projected to be available for projects after prior obligations is $45,308,124. | |
EVALUATION | |
SUBMITTED BY:
Amber Dickerson, Manager, Planning & Siting Lorraine Duffy Suarez, General Manager, Growth Management |
Christopher Farkas | Dr. Alberto Vázquez | |
Chief Operating Officer (813) 272-4004 |
Chief of Staff (813) 272-4986 |
|
C 7.02 | ||