HCPS FL Logo Operations
Action Item
DATE: Tuesday, May 15, 2018
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Construction Documents and Guaranteed Maximum Price (GMP) for Heating, Ventilating and Air Conditioning (HVAC) System Replacement at Crestwood Elementary School
EXECUTIVE SUMMARY
A previously approved District Facilities Five Year Work Program provides for heating, ventilating and air conditioning (HVAC) renovation at Crestwood Elementary School.  On September 19, 2017, the Board appointed SGM Engineering, Inc. and Walbridge Aldinger, LLC to provide design and construction management services. The project scope consists of the replacement of chiller plants, including system piping, air handling unit (AHU), ductwork, controls and test and balance to include assistance in the assessment of salvageable equipment and recovery of refrigerant.

Approval of the Guaranteed Maximum price (GMP) will establish the cost for the project.

Project completion is scheduled for July 31, 2018.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
Funds in the amount of $3,051,867.00 will be available in the Sales Tax Revenue and Community Investment Tax funds. For tracking purposes, the project number specific to this agenda item is 8200. As of Thursday, April 26, 2018, the remaining balance less encumbrances for this line item equaled $2,425,815.10.

The Guaranteed Maximum Price recommended for approval is $2,766,397.
EVALUATION
SUBMITTED BY:  Manuel Garcia, Jr., Project Administrator
    Christopher Farkas

  Chief Operating Officer
(813) 272-4004
    C 7.09
Hillsborough County Public Schools (Florida) * Mtg.#20180515_878 (Board Meeting followed by Public Hearing) * Section C Item# 7.09