Information Item
DATE: Tuesday, May 15, 2018
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Information and Plan Update for the Energy Management and Conservation Services Project with Minimise, USA, LLC (Business Services Division)
EXECUTIVE SUMMARY
As we work to reduce district expenditures in Energy Services, we are providing a project update on the Energy Efficiency Measures to date.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship
FINANCIAL IMPACT (Budgeted:  No)
EVALUATION
July 18, 2017 Information Rollout and plan update (completed)
 August 1, 2017 - Memorandum of Agreement Energy Survey, Minimise, USA, LLC (completed)
 August 9, 2017 - Provide electric bills for previous 24 months (completed)
 August 12, 2017 - Provide Building Site Blueprints (completed) 
 October 2, 2017 - Conduct three phases of Site Surveys (four months) 
 November 14, 2017 - Exhibit Items and progress of work update
 January 23, 2018 - Monthly update for Phase I
 February 20, 2018 - Amendments 1, 2, and 3 to update Shared Savings Plan Agreement
 May 15, 2018 - Project update and beyond
SUBMITTED BY: 
    Gretchen Saunders

  Chief Business Officer
(813) 272-4270
    C 13.02