HCPS FL Logo Operations
Action Item
DATE: Tuesday, July 17, 2018
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Roof Replacements at Two Sites (Lee, Hillsborough)
EXECUTIVE SUMMARY
A previously approved District Facilities Five Year Work Program provided for roof replacements at Lee Elementary and Hillsborough High Schools.  District staff selected Roof Engineering Associates, Inc. and R.W. Tymewell, Inc. from the approved continuing services consultants list to provide design and construction management services.  The scope of work included the reroof of Building 1 at Hillsborough High School and the replacement of the entire roof at Lee Elementary School. Although the work at Lee Elementary School was substantially complete, the project must be closed without final completion due to the fire that occurred in September 2017. 

The design professional has certified that the work is now fully complete at Hillsborough High School in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.  
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
Funds in the amount of $1,137,174.45 will be available in the Local Millage fund. For tracking purposes, the project number specific to this agenda item is 8238. As of Thursday, June 21, 2018, the remaining balance less encumbrances for this line item equaled $71,947.74.

Contract Status:

Guaranteed Maximum Price: $1,075,445.00
Approved Change Orders: $324,280.52 Credit (See Attachment)
Revised Guaranteed Maximum Price: $751,164.48
Payments to Date: $740,343.94
Balance Due: $10,820.54
Revised Construction Cost: $965,763.78

Required Substantial Completion Date: September 5, 2017
Approved Time Extension:  135 Calendar Days
Revised Required Substantial Completion Date:  January 18, 2018
Substantial Completion Date: January 18, 2018
EVALUATION
SUBMITTED BY:  Chuck Plante, Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004
    C 7.03
Hillsborough County Public Schools (Florida) * Mtg.#20180717_892 (Board Meeting) * Section C Item# 7.03