Action Item
DATE: Tuesday, September 11, 2018
TO: School Board Members
FROM: Jeff Eakins, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Roof and Kitchen Hood and Heating, Ventilating and Air Conditioning Roof Top Unit (HVAC RTU) Replacements at Six Sites (Ballast Point, Broward, Lomax, McLane, Gorrie, Webb)
EXECUTIVE SUMMARY
A previously approved District Facilities Five Year Work Program provided for replacement of kitchen hoods at Ballast Point, Broward, Lomax, and Gorrie Elementary and Webb Middle School, and replacement of the kitchen hood and selected HVAC RTUs at McLane Middle School. At Gorrie, Lomax and McLane, the kitchen and cafeteria roof surrounding the equipment also required replacement. District staff combined the requirements into a single project and selected Phoenix Engineering Group, Inc. and Kenyon & Partners, Inc. from the approved Continuing Services Consultants list to provide design and construction management services.

The design professional has certified that the work is now fully complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
Funds in the amount of $1,962,910.21 will be available in the Local Millage fund. For tracking purposes, the project number specific to this agenda item is 8100 / 8138 / 8597. As of Monday, August 20, 2018, the remaining balance less encumbrances for this line item equaled $167,381.97.

Contract Status:
Guaranteed Maximum Price: $1,697,955.00
Approved Change Orders: $464,904.11 Credit (See Attachment)
Revised Guaranteed Maximum Price: $1,233,050.89
Payments to Date: $1,078,862.88
Balance Due: $154,188.01
Revised Construction Cost: $1,589,343.49
EVALUATION
SUBMITTED BY:  Chuck Plante, Project Administrator
    Christopher Farkas

  Deputy Superintendent, Operations
(813) 272-4004