Operations
Action Item |
DATE: | Tuesday, February 5, 2019 |
TO: | School Board Members |
FROM: | Jeff Eakins, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Acceptance for Epoxy Pipe Lining at Thonotosassa Elementary and Tampa Bay Technical High Schools | |
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provides for restoring and applying an epoxy barrier coating to the galvanized and copper water piping in Buildings 1 through 15, including the galvanized main that services the buildings at Thonotosassa Elementary and restoring the galvanized and copper water piping in all buildings at Tampa Bay Technical High School using an epoxy lining.
The District's Maintenance Department has certified that the work is now fully complete in accordance with the plans, specifications and other contract documents which recommend Board Acceptance. |
|
STRATEGIC OBJECTIVES | |
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
Funds in the amount of $741,632.28 will be available in the PECO Maintenance fund. For tracking purposes, the project number specific to this agenda item is 8233. As of Thursday, January 17, 2019, the remaining balance less encumbrances for this line item equaled $19,582.04.
Contract Status: Contract Sum: $746,660.00 Approved Change Orders: Credit (See Attachment) $24,609.76 Revised Contract Sum: $722,050.24 Payments to Date: $656,529.26 Balance Due: $65,520.98 Revised Construction Cost: $722,050.24 Revised Substantial Completion Date: August 23, 2018 (Thonotosassa Elementary School) Approved Time Extension: 99 Calendar Days Revised Required Substantial Completion Date: November 30, 2018 Substantial Completion Date: August 23, 2018 Revised Substantial Completion Date: June 30, 2018 (Tampa Bay Technical High School) Approved Time Extension: 0 Calendar Days Substantial Completion Date: June 30, 2018 |
|
EVALUATION | |
SUBMITTED BY: Chuck Plante, Sr. Project Administrator |
Christopher Farkas | ||
Deputy Superintendent, Operations (813) 272-4004 |
||
C 7.01 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20190205_917 (Board Meeting) * Section C Item# 7.01 |