Operations
Action Item |
DATE: | Tuesday, January 23, 2018 |
TO: | School Board Members |
FROM: | Jeff Eakins, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Acceptance of Project for the Classroom Addition at East Bay High School | |
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provided for a classroom addition at East Bay High School to support current and project enrollment growth within existing boundaries. The project scope provided twenty new classrooms adding capacity for five hundred additional students. On November 17, 2015, the Board approved the appointment of Wilder Architecture, Inc. to provide design services and on December 15, 2015 appointed Ajax Building Corporation to provide construction management services.
The design professional has certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance. |
|
STRATEGIC OBJECTIVES | |
• Establish a strong foundation of financial stewardship • Demonstrate "best practices" in all aspects of safety: student, employee, visitor, facility, transportation, and health • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
Funds in the amount of $8,000,000.00 will be available in the Impact Fees fund. For tracking purposes, the project number specific to this agenda item is 8607. As of Thursday, December 14, 2017, the remaining balance less encumbrances for this line item equaled $1,382,194.87.
Guaranteed Maximum Price: $5,976,000.00 |
|
EVALUATION | |
SUBMITTED BY: Chuck Plante, Project Administrator |
Christopher Farkas | Jeffrey Eakins | |
Chief Operating Officer (813) 272-4004 |
Superintendent (813) 272-4047 |
|
C 7.04 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20180123_858 (Board Meeting) * Section C Item# 7.04 |