Approve Change Order Number Three for Cooling Tower Replacements at Blake High School
EXECUTIVE SUMMARY

On April 12, 2016, the Board approved an urgent requirement for replacement of the cooling towers and related equipment serving the HVAC cooling plant at Blake High School.  The reconciliation of direct purchases for the project requires a change order to adjust the contract amount.

Previous credits by the contractor to the District for the direct purchases significantly exceeded the amounts required.  As the resultant change order returning the excess funds to the contractor is for an amount greater than $100,000, Board approval is required. 

STRATEGIC OBJECTIVES
• Establish a strong foundation of financial stewardship • Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
Funds in the amount of $547,801.94 will be available in the Local Millage fund. For tracking purposes, the project number specific to this agenda item is 8597. As of Thursday, November 3, 2016, the remaining balance less encumbrances for this line item equaled $135,873.24.

The item is included in the District Capital Outlay:  Local Millage.

Contract Status:
Contract Sum:  $460,500.00
Approved Change Orders:  $171,600.00 Credit (See Attachment)
Change Order Recommended Herein:  $120,167.28 Extra (See Attachment)
Revised Contract Sum:  $409,067.28

Required Substantial Completion Date:  July 29, 2016
EVALUATION
SUBMITTED BY: 
Christopher Farkas   Dr. Alberto Vázquez
Chief Operating Officer
(813) 272-4004
  Chief of Staff
(813) 272-4986
    C 7.01
Hillsborough County Public Schools (Florida) * Mtg.#20161206_769 (Board Meeting) * Section C Item# 7.01