SOUTH COUNTY CAREER CENTER (PHASE 2)
REMODEL
APPROVAL OF CONSTRUCTION DOCUMENTS AND GUARANTEED MAXIMUM PRICE

EXECUTIVE SUMMARY

This project is being planned by the architectural firm of Holmes Hepner & Associates Architects. On March 7, 2000, the Board appointed the construction management firm of A.D. Morgan Corporation. The scope of work provides for the remodeling of Building 2 to include complete mechanical, electrical, plumbing, and interior finishes. This building will accommodate the Family and Consumer Sciences/General Education, Culinary Arts Laboratory and Sales Merchandising classrooms. This added scope will be accomplished under the terms of the existing agreements.

Approval of the guaranteed price will provide a maximum cost for the facility. Project completion is scheduled for September 15, 2005.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $1,722,912. The construction budget is $1,722,912. This item is included in the District Capital Outlay: Capital Outlay and Debt Service.

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.05e
Hillsborough County Public Schools (Florida) * Mtg.#20050906_151 * Section E Item# 6.05e