Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, September 6, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

RAMPELLO DOWNTOWN SCHOOL PARKING FACILITY
APPROVAL OF CHANGE ORDER NO. 1 - $18,422.00 EXTRA / 97 CALENDAR DAY TIME EXTENSION

EXECUTIVE SUMMARY

On October 19, 2004, the Board appointed J.O. DeLotto & Sons, Inc. to provide design-build services for the Rampello Downtown School Parking Facility. The scope of work provides for construction of a new parking garage to house 450 automobiles.

This change order provides for fill dirt and soil density testing necessitated by excavation of a fuel oil tank and surrounding contaminated soil. It also provides a time extension for completion of the work.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

N/A

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2004.

Contract Status:
Guaranteed Maximum Price: $5,444,096.00
Change Order Recommended Herein: $18,422.00 Extra
Revised Guaranteed Maximum Price: $5,462,518.00

Original Completion Date: December 20, 2005
Time Extension Recommended Herein: 97 calendar days
Revised Completion Date: March 27, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.10
Hillsborough County Public Schools (Florida) * Mtg.#20050906_151 * Section E Item# 6.10