Facilities Action Item |
DATE: Tuesday, October 25, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of John J. McKenna, Architect. On January 13, 2004, the Board appointed the construction management firm of Vogel Bros. Building Co. in association with CDC. The scope of work includes replacement of selected HVAC system components, and repair to finishes damaged during the work.
Change Order No. 5 provides for Board Room modifications to accommodate the new podium and electronics, and correct handicap code deficiencies. A time extension of 21 calendar days is included for completion of work. Change Order No. 6 provides for demolition and replacement of kitchen ductwork, installation of acoustical duct lining in the 3rd floor return air system and selected new finishes in kitchen, servery, and dining areas; modifications of control valves in hot water heating system, and removal of piping serving abandoned solar heating system. A time extension of 3 calendar days is included for completion of work.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.10 | |
Hillsborough County Public Schools (Florida) * Mtg.#20051025_158 * Section E Item# 6.10 |