Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, February 7, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

MULLER MAGNET ELEMENTARY SCHOOL
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 6 - $9,788.87 EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Robbins, Bell & Kreher Architects. On February 6, 2001, the Board appointed the construction management firm of Beck, Ltd.

This change order provides for replacement of door lites and frames in Building 4 with impact resistant glass to meet Emergency Hurricane shelter criteria. It also provides for increases in steel and electrical costs totaling $15,656 of which one third in the amount of $5,218.67 will be paid by the District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.

Contract Status:
Guaranteed Maximum Price: $6,437,017.00
Change Orders Previously Approved: $1,180,235.35 Credit
Change Order Recommended Herein: $9,788.87 Extra
Revised Guaranteed Maximum Price: $5,266,570.52

Original Completion Date: July 27, 2003
Time Extension Previously Approved: 90 calendar days
Revised Completion Date: October 25, 2003

EVALUATION

N/A

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004