This project was planned by the architectural firm of Robbins, Bell & Kreher Architects. On February 6, 2001, the Board appointed the construction management firm of Beck, Ltd.
This change order provides for replacement of door lites and frames in Building 4 with impact resistant glass to meet Emergency Hurricane shelter criteria. It also provides for increases in steel and electrical costs totaling $15,656 of which one third in the amount of $5,218.67 will be paid by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |