This project was planned by the architectural firm of Woodroffe Corporation Architects. On November 18, 2003, the Board appointed the construction management firm of Hardin Construction. This new facility is a reuse of the Chiles Elementary School design. Based on the current boundaries, relief has been provided for Clark, Heritage, Hunter's Green, and Pride Elementary Schools.
This change order provides a credit for the direct purchase of materials by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by the District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
Thomas J. Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.08 | |
Hillsborough County Public Schools (Florida) * Mtg.#20051108_159 * Section E Item# 6.08 |