Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, November 8, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

LEWIS ELEMENTARY SCHOOL
EXTERIOR REPAIRS AND WATERPROOFING
APPROVAL OF CHANGE ORDER NO. 1- $1,270.00 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Elements Architects. J.B.D. Construction, Inc. is providing construction management services under their continuing services agreement. The scope of work includes brick repair and replacement, concrete and stucco repairs, repainting, and expansion joint replacement.

This change order provides a credit for the return of unused contingency funds.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: 2 Mill.
Contract Status:
Guaranteed Maximum Price: $82,094.00
Change Order Recommended Herein: $1,270.00 Credit
Revised Guaranteed Maximum Price: $80,824.00
Contract Completion Date: January 13, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.07
Hillsborough County Public Schools (Florida) * Mtg.#20051108_159 * Section E Item# 6.07