EXECUTIVE SUMMARY
Newsome High School was planned by the architectural firm of Holmes Hepner & Associates Architects. On March 13, 2001, the Board appointed the construction management firm of Beck, Ltd. On August 24, 2004, the Board approved Amendment No. 2 to the construction management agreement for construction of an athletic complex. The scope of work included a football field grandstand, baseball and softball field bleachers, dugouts, a press box, batting cages, a concession building and restrooms.
This change order provides a credit for the return of unused contingency funds.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 1999.
Contract StatusEVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.12 | |
Hillsborough County Public Schools (Florida) * Mtg.#20051122_161 * Section E Item# 6.12 |