Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, November 22, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

MIDDLE SCHOOL "RR" (NORTHWEST)
NEW FACILITY
APPROVAL OF SCHEMATIC DESIGN PHASE

EXECUTIVE SUMMARY

This project is being planned by the architectural firm of Wilder Architecture, Inc. On June 7, 2005, the Board appointed the construction management firm of Allstate Construction, Inc. As of the current boundaries, relief will be provided for Davidsen, Farnell, and Martinez Middle Schools.

Approval of the schematic design will allow the architect to proceed with design development. Project completion is scheduled for the 2008-09 school year.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

Construction budget is $16,702,007. The estimate of probable cost is $16,607,551. This item is included in the District Capital Outlay: Certificates of Participation Series 05.

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.04b