Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 13, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

MACFARLANE PARK ELEMENTARY SCHOOL
ADDITION AND RENOVATION
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Carruthers & Associates Architects with Allstate Construction providing construction management services under their continuing services agreement. The scope of work included the addition of a media center and expansion of the existing cafeteria.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2001.

Contract Status:
Guaranteed Maximum Price: $995,600.00
Change Orders Previously Approved: $292,975.10 Extra
Revised Guaranteed Maximum Price: $1,288,575.10
Payments to Date: $1,287,575.10
Balance Due: $1,000.00

Original Completion Date: August 2, 2004
Time Extensions Previously Approved: 361 calendar days
Revised Completion Date: July 29, 2005
Substantial Completion Date: September 21, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004