Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, January 17, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

DOBY ELEMENTARY SCHOOL
NEW FACILITY
APPROVAL OF CONSTRUCTION DOCUMENTS AND GUARANTEED MAXIMUM PRICE

EXECUTIVE SUMMARY

On June 7, 2005, the Board appointed Carruthers & Associates - Architects, P.A. and Greater Bay Construction, Inc. to provide design and construction management services. This new facility will relieve overcrowding at Apollo Beach, Corr, and Sessums Elementary Schools.

Approval of the guaranteed price will provide a maximum cost for the facility. Project completion is scheduled for July 31, 2006.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $10,769,449. The construction budget is $10,769,449. This item is included in the District Capital Outlay: Community Investment Tax 04 and Classrooms for Kids 05.

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.01e
Hillsborough County Public Schools (Florida) * Mtg.#20060117_165 * Section E Item# 6.01e