MULLER MAGNET ELEMENTARY SCHOOL
NEW FACILITY
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Robbins, Bell & Kreher Architects. On February 6, 2001, the Board appointed the construction management firm of Beck, Ltd.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.

Contract Status:
Guaranteed Maximum Price: $6,437,017.00
Change Orders Previously Approved: $1,170,446.48 Credit
Revised Guaranteed Maximum Price: $5,266,570.52
Payments to Date: $5,231,781.65
Balance Due: $34,788.87

Original Completion Date: July 27, 2003
Time Extensions Previously Approved: 90 calendar Days
Revised Completion Date: October 25, 2003
Substantial Completion Date: August 5, 2003

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.19
Hillsborough County Public Schools (Florida) * Mtg.#20060221_170 * Section E Item# 6.19