Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, March 14, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

BARTELS MIDDLE SCHOOL
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 3 - $696,209.58 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Long & Associates, Inc. On November 18, 2003, the Board appointed the construction management firm of Hardin Construction. This new facility is located in the New Tampa area and is a reuse of the Shields Middle School design. As of the current boundaries, relief will be provided for Benito and Liberty Middle Schools.

This change order provides credits to the Direct Purchase and Owner Controlled Insurance Programs.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2004C and 2002.

Contract Status:
Guaranteed Maximum Price: $18,517,742.00
Change Orders Previously Approved: $1,977,706.88 Credit
Change Order Recommended Herein: $696,209.58 Credit
Revised Guaranteed Maximum Price: $15,843,825.54

Contract Completion Date: August 1, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.07
Hillsborough County Public Schools (Florida) * Mtg.#20060314_172 * Section E Item# 6.07