BAY CREST ELEMENTARY SCHOOL - RENOVATION / CLASSROOMS FOR KIDS ADDITION
APPROVAL OF CHANGE ORDER NO. 3 (RENOVATION) - $20,262.91 EXTRA
APPROVAL OF CHANGE ORDER NO. 3 (CLASSROOMS FOR KIDS) - $11,080.13 EXTRA
APPROVAL OF CHANGE ORDER NO. 4 (RENOVATION) - $312,978.85 CREDIT
APPROVAL OF CHANGE ORDER NO. 4 (CLASSROOMS FOR KIDS) - $51,171.77 NET CREDIT
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

These projects were planned by the architectural firm of Carruthers & Associates. On January 13, 2004, the Board appointed the construction management firm of Christiano Construction Company, Inc. The scope of renovation included new carpet, vinyl composition tile (VCT) flooring, acoustical ceilings, intercom, fire alarm, telephone, data, security, closed circuit television (CCTV), and master key systems. It also provided for replacement of lighting fixtures, door hardware, heating, ventilation and air conditioning system (HVAC), painting, roofing, Americans with Disabilities Act (ADA) improvements, casework refurbishment, and miscellaneous deep cleaning, sealant, drainage and minor repair work. In addition, 12 primary classrooms were added to meet class size reduction requirements.

Change Order No. 3 (Renovation) provides for the final reconciliation of the Direct Purchase Program. Change Order No. 3 (CFK) provides for adjustments to the Direct Purchase Program. Change Order No. 4 (Renovation) provides credits for project savings, return of unused contingency funds, and final reconciliation of the Owner Controlled Insurance Program. Change Order No. 4 (CFK) provides credits for project savings and return of unused contingency funds. It also provides for the final reconciliation of the Direct Purchase and Owner Controlled Insurance Programs.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

These items are included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction for the renovation and Classrooms For Kids (CFK) and District Effort Recognition for the CFK addition.
Contract Status (Renovation): See Attachment
Guaranteed Maximum Price: $2,217,329.57
Contract Status (CFK): See Attachment
Guaranteed Maximum Price: $1,073,418.21

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.21
Hillsborough County Public Schools (Florida) * Mtg.#20060502_175 * Section E Item# 6.21