Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, March 14, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

SPOTO HIGH SCHOOL
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 7 - $62,505.00 NET CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Sylla, Inc. On November 18, 2003, the Board appointed the construction management firm of HC Beck, Ltd. The facility is a reuse of the Middleton High School design. This new facility will relieve overcrowding at East Bay and Riverview High Schools.

This change order provides credits for deletion of special soil mixture at athletic fields, and low voltage lighting in Auditorium. It also provides for the addition of electrical and communication systems to the press boxes, and a mulch bin for the Agriculture program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2003 (new facility), and Certificates of Participation Series 1999 (athletic facility).
Contract Status:
Guaranteed Maximum Price: $33,178,803.00
Change Orders Previously Approved: $8,710,116.65 Credit
Change Order Recommended Herein: $76,835.00 Credit and $14,330.00 Extra
Revised Guaranteed Maximum Price: $24,406,181.35

Contract Completion Date: November 18, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.12
Hillsborough County Public Schools (Florida) * Mtg.#20060314_172 * Section E Item# 6.12