Facilities Action Item |
DATE: Tuesday, May 2, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On June 7, 2005, the Board appointed Carruthers & Associates - Architects, P.A. and Greater Bay Construction, Inc. to provide design and construction management services. This new facility will relieve overcrowding at Apollo Beach, Corr, and Sessums Elementary Schools and will open in August 2006.
Change Order No. 2 provides for a revision to the kitchen ceiling grid and the addition of a structural footing at a masonry partition. Change Order No. 3 provides for a fire sprinkler system in Buildings 2 and 4.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Community Investment Tax 04 and Classrooms for Kids.
Contract Status:
Guaranteed Maximum Price: $10,769,449.00
Change Order Previously Approved: $1,904,190.41 Credit
Change Order No. 2 Recommended Herein: $5,737.00 Extra
Change Order No. 3 Recommended Herein: $162,285.00 Extra
Revised Guaranteed Maximum Price: $9,033,280.59
Contract Completion Date: July 31, 2006
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |