Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, April 19, 2005
TO: School Board Members
FROM: Earl J. Lennard, Superintendent

SUBJECT / RECOMMENDATIONS

NATURE'S CLASSROOM - SITE ELECTRICAL SERVICE UPGRADE
APPROVAL OF EXPENDITURE

EXECUTIVE SUMMARY


This project is being planned by the engineering firm Anston-Greenlees Inc. as a pro bono effort to assist the District. The scope of work includes upgraded electrical service and new data, CCTV, fire alarm, telephone, and security systems required to support the Administration building, Environmental Studies building, and other facilities on the Nature’s Classroom campus.



Approval of this expenditure will allow the work to be awarded to the lowest bidder, Energy Electric.



ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)


Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.



FINANCIAL IMPACT (Budgeted: Yes)


The cost of this project is $211,178. This item is included in the District Capital Outlay: 2 Mill.





EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
MaryEllen Elia
Chief Facilities Officer
(813) 272-4004
6.02
Hillsborough County Public Schools (Florida) * Mtg.#20050419_138 * Section E Item# 6.02