This project was planned by the architectural firm of Reynolds Smith & Hills, Inc. On March 12, 2002, the Board appointed the construction management firm of Christiano Construction Company. The scope of work included roof replacement, cleaning of exterior brick, replacement of exterior doors and hardware, construction of a covered bus drop-off area, renovation of HVAC, electrical, plumbing, and life safety systems, ceiling and floor replacement, painting, technology infrastructure networking, and code compliance corrections.
This change order provides credits for project savings and the return of unused contingency funds. It also provides for the final reconciliation of the Direct Purchase Program.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |