B.T. WASHINGTON K-8 SCHOOL - ADDITION AND RENOVATION
APPROVAL OF CHANGE ORDER NO. 11 - $37,414.00 EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Rick Z. Smith & Associates Architects, Inc. On March 12, 2002, the Board appointed the construction management firm of R.J. Bunbury Company, Inc. The scope of work for the conversion of B.T. Washington from a middle school to K-8 is as follows: the existing parking lots were modified, resurfaced, and re-striped to better accommodate the elementary and middle school programs. Areas of poor drainage, missing gutters and downspouts were corrected. Buildings 1, 2 and 3 were remodeled for better utilization and to meet current Code requirements. There was an addition of a Science lab and two Science classrooms. Building 4 was demolished and a new building was constructed to house 8 classrooms. Existing main electrical service, fire alarm, security, intercom, telephone and data systems, lighting, casework, teaching aids, and ceilings were replaced campus-wide. Mechanical system revisions were made to upgrade the toilet room exhausts, and replace the air handler in administration. The entire campus was painted. Floor finish replacement was handled on a room-by room basis.

This change order is required to reroute underground sewer, rework kitchen exhaust duct, repair existing boiler and air conditioning equipment, add chase walls and power outlets, revise ceiling design, replace existing chiller drive for pump, change new elevator to key-operated, and provide missing expansion joint covers.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.
Contract Status: Guaranteed Maximum Price: $4,062,861.00
Change Orders Previously Approved: $730,474.20 Credit
Change Order Recommended Herein: $37,414.00 Extra
Revised Guaranteed Maximum Price: $3,369,800.80
Contract Completion Date: August 22, 2004
Time Extension Previously Approved: 28 Calendar Days
Revised Completion Date: August 22, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
MaryEllen Elia
Chief Facilities Officer
(813) 272-4004
6.08
Hillsborough County Public Schools (Florida) * Mtg.#20050503_140 * Section E Item# 6.08