Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 11, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

HILLSBOROUGH HIGH SCHOOL
GYMNASIUM REMODEL / ROTC RENOVATION
AWARD OF CONTRACT


EXECUTIVE SUMMARY

This project is being planned by the architectural firm of Wilder Architecture, Inc. The scope of work provides for remodel of existing Gymnasium and renovation of a single story wing used for ROTC and classrooms. The project was advertised and bids received (see attachment A). The low bidder, Greater Bay Construction Company, Inc., is recommended. Project completion is scheduled for April 16, 2007.


ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.


FINANCIAL IMPACT (Budgeted: Yes)

Total funds in the amount of $4,018,300 are included in the District Capital Outlay: Community Investment Tax 2006. The contract amount being awarded is $4,018,300 (Base Bid of $4,073,000 and deductive alternates 2 and 4 in the amount of $54,700. See attachment B).


EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.04b
Hillsborough County Public Schools (Florida) * Mtg.#20060711_179 * Section E Item# 6.04b