Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 11, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

FRANKLIN MIDDLE SCHOOL
RENOVATIONS AND GYMNASIUM ADDITION
APPROVAL OF CHANGE ORDER NO. 19 - $8,015.50 EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Howard and Associates, Architects, PA. On March 12, 2002, the Board appointed the construction management firm of The Morganti Group. The scope of work includes the addition of a new gymnasium and elevator. Also included is the renovation of existing classrooms, administration offices, and the auditorium to accommodate the new magnet program.

This change order provides for a new scoreboard, electric motors for basketball goals, new duct heater and related electrical revisions, relocation of plumbing fixtures, and fire-rating modifications.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax and 2 Mill.
Contract Status:
Guaranteed Maximum Price: $4,600,000.00
Change Orders Previously Approved: $3,124,203.96 Extra
Change Order Recommended Herein: $8,015.50 Extra
Revised Guaranteed Maximum Price: $7,732,219.46
Revised Construction Cost: $8,720,154.02

Original Completion Date: September 1, 2004
Time Extensions Previously Approved: 332 calendar days
Revised Completion Date: July 30, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.08
Hillsborough County Public Schools (Florida) * Mtg.#20060711_179 * Section E Item# 6.08