CARVER CENTER
REPLACEMENT FACILITY
APPROVAL OF CHANGE ORDER NO. 2 - $142,540.00 EXTRA

EXECUTIVE SUMMARY

The existing Carver Center was razed to accommodate the widening of the adjacent interstate highway. As a consequence, the programs were relocated to another facility. The former site of the Bryan Alternative Center was identified as the most suitable location for the replacement facility. The Board previously commissioned the architectural firm of Howard & Associates, Architects, PA to expedite the adaptation of an existing design to house the Carver programs. The Board approved the previously appointed firm of J.O. DeLotto and Sons, Inc. to manage the construction of this new facility.

This change order provides for cost to expedite project.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

Funding will be derived from land proceeds and Individuals with Disabilities Education Act and School Infrastructure Thrift Award.

Contract Status:
Guaranteed Maximum Price: $5,635,451.00
Change Order Previously Recommended: $938,403.68 Credit
Change Order Recommended Herein: $142,540.00 Extra
Revised Guaranteed Maximum Price: $4,839,587.32
Revised Construction Cost: $5,724,024.75

Contract Completion Date: January 26, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.07
Hillsborough County Public Schools (Florida) * Mtg.#20060711_179 * Section E Item# 6.07