Facilities Action Item |
DATE: Tuesday, August 8, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Long & Associates, Inc. On March 12, 2002, the Board appointed the construction management firm of Christiano Construction Company, Inc.
This change order provides an adjustment to the Direct Purchase and Owner Controlled Insurance Programs.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2001.
Contract Status:
Guaranteed Maximum Price: $5,448,174.00
Change Orders Previously Approved: $908,923.52 Credit
Change Order Recommended Herein: $1,494.43 Extra
Revised Guaranteed Maximum Price: $4,540,744.91
Revised Construction Cost: $5,296,738.74
Original Completion Date: July 14, 2004
Time Extension Previously Approved: 70 calendar days
Revised Completion Date: September 22, 2004
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.05 | |
Hillsborough County Public Schools (Florida) * Mtg.#20060808_181 * Section E Item# 6.05 |