Facilities Action Item |
DATE: Tuesday, September 26, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On April 4, 2006, the Board approved the appointment of John J. McKenna Architect P.A. for architectural services. The scope of renovation includes new roofing, air conditioning equipment and ductwork, upgraded low voltage and electrical systems, flooring, canopy for Building 1, handicap accessibility modifications, and reconfiguration of existing bus and parent driveways.
Approval of the design development phase will allow the architect to proceed with construction documents. Project completion is scheduled for December 2007.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.
FINANCIAL IMPACT (Budgeted: Yes)
The project is currently funded at $4,350,000. The estimate of probable cost is $4,347,207. This item is included in the District Capital Outlay: Community Investment Tax.
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.06 | |
Hillsborough County Public Schools (Florida) * Mtg.#20060926_184 * Section E Item# 6.06 |