On April 4, 2006, the Board approved the appointment of Long & Associates, Inc. for architectural services. The scope of renovation includes new roofing and bus pick-up canopy, upgrades to air conditioning, electrical and communication systems, and expansion of the student dining room.
Approval of the design development phase will allow the architect to proceed with construction documents. Project completion is scheduled for December 2007.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.
FINANCIAL IMPACT (Budgeted: Yes)
This project is currently funded at $2,900,000. The estimate of probable cost is $2,851,438. This item is included in the District Capital Outlay: Community Investment Tax.
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.10B | |
Hillsborough County Public Schools (Florida) * Mtg.#20061010_185 * Section E Item# 6.10B |