Facilities Action Item |
DATE: Tuesday, November 21, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Alfonso Architects. On March 12, 2002, the Board appointed the construction management firm of J.O. DeLotto & Sons, Inc. The scope of work included construction of a new K-8 school to house 1226 students.
This change order provides for hardware and frame fasteners upgrade to comply with product approval requirements.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2003 and Community Investment Tax.
Contract Status:
Guaranteed Maximum Price: $11,277,514.00
Change Orders Previously Approved: $1,623,663.78 Credit
Change Order Recommended Herein: $18,419.00 Extra
Revised Guaranteed Maximum Price: $9,672,269.22
Revised Construction Cost: $11,905,958.83
Original Completion Date: May 6, 2005
Time Extension Previously Approved: 21 Calendar Days
Revised Completion Date: May 27, 2005
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.05 | |
Hillsborough County Public Schools (Florida) * Mtg.#20061121_188 * Section E Item# 6.05 |