Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, November 21, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

RAMPELLO DOWNTOWN PARTNERSHIP SCHOOL
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 9 - $18,419.00 EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Alfonso Architects. On March 12, 2002, the Board appointed the construction management firm of J.O. DeLotto & Sons, Inc. The scope of work included construction of a new K-8 school to house 1226 students.

This change order provides for hardware and frame fasteners upgrade to comply with product approval requirements.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2003 and Community Investment Tax.

Contract Status:
Guaranteed Maximum Price: $11,277,514.00
Change Orders Previously Approved: $1,623,663.78 Credit
Change Order Recommended Herein: $18,419.00 Extra
Revised Guaranteed Maximum Price: $9,672,269.22
Revised Construction Cost: $11,905,958.83

Original Completion Date: May 6, 2005
Time Extension Previously Approved: 21 Calendar Days
Revised Completion Date: May 27, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.05
Hillsborough County Public Schools (Florida) * Mtg.#20061121_188 * Section E Item# 6.05