Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 3, 2005
TO: School Board Members
FROM: Earl J. Lennard, Superintendent

SUBJECT / RECOMMENDATIONS

GARY ADULT CENTER AND ADULT EDUCATION DISTRICT OFFICES
REASSIGNMENT OF CONSTRUCTION MANAGER AGREEMENT

EXECUTIVE SUMMARY

On March 12, 2002, the Board approved the appointment of Rick Rados Architecture and Cutler Associates to design and construct a replacement facility for the Gary Adult Center. On April 6, 2004, the Board reassigned the architectural agreement to Wilder Architecture, Inc.

A reassignment of construction manager is necessary due to the withdrawal of Cutler Associates from the project. Peter R. Brown Construction, Inc. was the second in the order of priority for the project. The reassignment of the construction manager agreement to Peter R. Brown Construction, Inc., with a fee of $185,000, will ensure the availability of sufficient resources to meet all project requirements.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

The construction budget is $4,029,162. This item is included in the District Capital Outlay: Community Investment Tax.

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
MaryEllen Elia
Chief Facilities Officer
(813) 272-4004
8.01D
Hillsborough County Public Schools (Florida) * Mtg.#20050503_140 * Section E Item# 8.01D