Facilities Action Item |
DATE: Tuesday, January 16, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On September 7, 2004, the Board appointed Schenkel Shultz Architecture and Turner Construction to provide design and construction management services for classroom additions at Boyette Springs, Cimino, Kingswood, Riverview, and Ruskin Elementary Schools. These additions are necessary to meet class size reduction requirements. The scope of work provides for the construction of 16 additional classrooms at Boyette Springs, Cimino, and Ruskin Elementary Schools, and 10 additional classrooms at Kingswood and Riverview Elementary Schools.
This change order provides for final reconciliation of the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
These items are included in the District Capital Outlay: Classrooms for Kids (Boyette Springs, Cimino, Riverview, and Ruskin Elementary Schools) and Certificates of Participation Series 2001 (Kingswood Elementary School).
Contract Status:
Guaranteed Maximum Price: $8,888,986.00
Change Orders Previously Approved: $837,766.97 Credit
Change Order Recommended Herein: $548,953.86 Credit
Revised Guaranteed Maximum Price: $7,502,265.17
Revised Construction Cost: $9,145,043.01
Original Completion Date: May 11, 2006
Time Extension Previously Approved: 3 Calendar Days
Revised Completion Date: May 14, 2006
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.11 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070116_228 * Section E Item# 6.11 |