Facilities Action Item |
DATE: Tuesday, January 16, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
The existing Instructional Services Center had exceeded its useful life and was demolished to allow construction of a two-story 100,000 square foot office building. On March 8, 2005, the Board appointed the design-build firm of R.R. Simmons Construction Corporation to provide design and construction management services.
Change Orders No. 1 and 2 provide credits for the direct purchase of materials by the District. Change Order No. 3 provides a time extension to incorporate tenant improvement changes.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Land Proceeds and Certificates of Participation Series 04C.
Contract Status:
Guaranteed Maximum Price: $8,910,763.00
Change Order No. 1 Recommended Herein: $1,082,334.57 Credit
Change Order No. 2 Recommended Herein: $20,980.81 Credit
Change Order No. 3 Recommended Herein: $0.00 Extra
Revised Guaranteed Maximum Price: $7,807,447.62
Revised Construction Price: $8,847,772.89
Original Completion Date: May 25, 2007
Time Extension Recommended in Change Order No. 3: 21 Calendar Days
Revised Completion Date: June 15, 2007
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.19 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070116_228 * Section E Item# 6.19 |