CAHOON ELEMENTARY SCHOOL
RENOVATIONS AND REMODELING 2004
APPROVAL OF CHANGE ORDER NO. 2 - $117,341.13 CREDIT
APPROVAL OF CHANGE ORDER NO. 3 - $66,076.00 CREDIT
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

Cahoon Elementary School completed a renovation and remodeling project which was accepted in October 2004. Additional funding was identified to provide needed improvements not included in the original scope of work. Existing agreements with Carruthers & Associates Architects P. A. and R. J. Bunbury Company, Inc. were amended to perform this work. The scope of work included administration renovations, replacement of heating, ventilating and air conditioning, lighting in Buildings 11, 12, and 13, site and drainage improvements, and other minor renovations.

Change Order No. 1 provided for additions to project scope for previously deleted work. It also provided for exterior painting of the Media Center, and for range installation modifications in the Head Start Classroom. A time extension was included for completion of the work. Change Order No. 2 provides a credit for final adjustment to the Direct Purchase Program. Change Order No. 3 provides credits for project savings and the return of unused contingency funds. The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Qualified Zone Academy Bonds Funds and 2 Mill.
Contract Status:
Guaranteed Maximum Price: $450,870.00
Change Order No. 1 Previously Approved: $500,000 Extra
Change Order No. 2 Recommended Herein: $117,341.13 Credit
Change Order No. 3 Recommended Herein: $66,076.00 Credit
Revised Guaranteed Maximum Price: $767,452.87
Payments to Date: $744,077.46
Balance Due: $23,375.41
Revised Construction Cost: $877,966.12
Contract Completion Date: August 29, 2005
Substantial Completion Date: August 29, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.23
Hillsborough County Public Schools (Florida) * Mtg.#20070116_228 * Section E Item# 6.23