Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, February 13, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

GORRIE ELEMENTARY SCHOOL
ADDITION, REMODEL, AND RENOVATE
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Robbins, Bell & Kreher, Inc. On May 1, 2001, the Board appointed the construction management firm of Kalemeris Construction, Inc. New construction included the addition of four kindergarten classrooms and a new media center. Renovations provided for upgrades to the existing buildings, including door replacement, wall upgrades, and ceiling, flooring, paint, cabinets, plumbing, heating, ventilating, and air conditioning (HVAC) and electrical work.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2000.
Contract Status:
Guaranteed Maximum Price: $1,948,696.00
Change Orders Previously Approved: $290,802.38 Credit
Revised Guaranteed Maximum Price: $1,657,893.62
Payments to Date: $1,600,695.16
Balance Due: $57,198.46
Revised Construction Cost: $2,239,220.35

Original Completion Date: December 30, 2003
Time Extension Previously Approved: 30 Calendar Days
Revised Completion Date: January 29, 2004
Substantial Completion Date: July 7, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.15a
Hillsborough County Public Schools (Florida) * Mtg.#20070213_231 * Section E Item# 6.15a