Facilities Action Item |
DATE: Tuesday, May 8, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the engineering firm of Ruyle Hayes + Jennewein Architects, P.A. On June 6, 2006, the Board appointed the firm of Gemini, Inc. for project completion. The scope of work provided for complete exterior painting and waterproofing, and replacement of selected windows.
Change Order No. 1 provides preparation, priming, and painting of the interior face of exterior doors on all buildings slated for exterior painting, and an additional finish coat on exterior doors and canopy support poles. A time extension is included for completion of the work. Change Order No. 2 provides for final reconciliation of the Direct Purchase Program.
The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: 2 Mill.
Contract Status:EVALUATION
SUBMITTED BY:
Rory Salimbene
General Manager of Maintenance (813) 635-1101 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.14 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070508_241 * Section E Item# 6.14 |