EXECUTIVE SUMMARY
On April 6, 2006, the Board approved the appointment of Carruthers & Associates Architects P.A. for architectural services. On January 16, 2007, the Board appointed the construction management firm of Manhattan Construction Company. The renovation of existing facilities provides for replacement of intercom, fire alarm, heating, ventilating and air conditioning (HVAC) systems, roofing, miscellaneous finishes, Americans with Disabilities Act (ADA) upgrades, and new freezer and hood in kitchen.
Approval of the guaranteed price will provide a maximum cost for the facility. Project completion is scheduled for December 11, 2007.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $3,300,000. The construction budget is $3,300,000. This item is included in the District Capital Outlay: Community Investment Tax.
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |