This project was planned by the architectural firm of Cooper Johnson Smith Architects. On November 18, 2003, the Board appointed the construction management firm of Batson-Cook Company. This new facility was a reuse of the Bevis Elementary School design.
Change Order No. 3 provides final reconciliation of the Direct Purchase and Owner Controlled Insurance Programs. Change Order No. 4 provides credits for project savings and the return of unused contingency funds.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.16 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070410_238 * Section E Item# 6.16 |