DATE: Tuesday, April 24, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

HILLSBOROUGH HIGH SCHOOL
GYMNASIUM REMODEL / ROTC RENOVATION
APPROVAL OF CHANGE ORDER NO. 3 - $46,035.53 NET EXTRA
APPROVAL OF CHANGE ORDER NO. 4 - $265,797.63 EXTRA / 107 CALENDAR DAY TIME EXTENSION

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Wilder Architecture, Inc. On July 11, 2006, the Board awarded the contract to the low bidder, Greater Bay Construction Co., Inc. The scope of work provides for remodel of existing Gymnasium and renovation of a single story wing used for ROTC and classrooms.

Change Order No. 3 provides temporary fencing, data cabling, asbestos removal, manhole modifications, opening for door at south side of Gymnasium for under bleacher access, and replacement of deleted Arms Room masonry wall from scope with metal framing and plywood with drywall. Credits provided for scope deletions include removal of entry masonry wall, finish on south wall of Room 150B, two windows at east end of Gymnasium, wood blocking in acoustical deck, operable wall (replaced with standard gypsum wall board partition), and chase wall at Gymnasium group toilets (replaced with furring of existing masonry wall). A credit is included for correction of an error in Change Order No. 1 regarding the construction manager's overhead and profit. Change Order No. 4 provides for General Conditions and a time extension resulting from concealed and unknown conditions discovered during demolition.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2006.
Contract Status:
Contract Sum: $4,018,300.00
Change Orders Previously Approved: $404,375.13 Credit
Change Order No. 3 Recommended Herein: $72,539.80 Extra and $26,504.27 Credit
Change Order No. 4 Recommended Herein: $265,797.63 Extra
Revised Contract Sum: $3,925,758.03
Revised Construction Cost: $4,341,659.10

Original Completion Date: April 16, 2007
Time Extension Recommended in Change Order No. 4: 107 Calendar Days
Revised Completion Date: August 1, 2007

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.17
Hillsborough County Public Schools (Florida) * Mtg.#20070424_239 * Section E Item# 6.17