Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 8, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

RUSKIN ELEMENTARY SCHOOL
RENOVATION
APPROVAL OF CONSTRUCTION DOCUMENTS AND GUARANTEED MAXIMUM PRICE

EXECUTIVE SUMMARY

This project is being planned by the architectural firm of Wilder Architecture, Inc. On January 16, 2007, the Board appointed the construction management firm of Horus Construction Services, Inc. The scope of renovation includes new instructional aids and finishes, modifications to air conditioning, communication, power, and lighting systems, site grading and drainage improvements, and demolition of the original 1940's structure which includes the classrooms, cafeteria, and kitchen.

Approval of the guaranteed price will provide a maximum cost for the facility. Project completion is scheduled for December 11, 2007.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $3,435,865.25. The construction budget is $3,450,000. This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO 05-06).

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.06b
Hillsborough County Public Schools (Florida) * Mtg.#20070508_241 * Section E Item# 6.06b