Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 8, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

ANCILLARY OFFICE BUILDING (INSTRUCTIONAL SERVICES CENTER)
3993 21ST AVENUE
INTERIORS OF NEW FACILITY
APPOINTMENT OF CONSTRUCTION MANAGER

EXECUTIVE SUMMARY

Proposals for construction management services were accepted on April 27, 2007. A Public Announcement was issued and a tabulation made of the firms that responded to the legal advertisement. The Professional Services Selection Committee convened the week of April 30 to review submittals and develop a short-list. Prospective providers were evaluated in accordance with the "Consultant's Competitive Negotiation Act," "State Requirements for Education Facilities," and School Board policy. On May 2, the Committee reviewed the short-listed applicants using a rubric and authorized staff to proceed with fee negotiations with the top-ranked firm. Negotiations are now complete and Board approval is required for formal appointment of the following firm:

  • The Morganti Group, Inc. for a fixed fee of $200,700.

  • * Attachment A - Public Announcement
    * Attachment B - Tabulation of Construction Management Firms
    * Attachment C - Professional Services Selection Committee Members
    * Attachment D - Standard Evaluation Criteria
    * Attachment E - Interview Rubric
    * Attachment F - Scores after Selection Committee Evaluation of Initial Submittals
    * Attachment G - Committee Scores on Short-Listed Firms' Presentations


    The listed fee is established in proportion to the stated construction budget and identified scope of work. Subsequent revision of either the construction budget or scope of work may warrant proportionate adjustment of the fee.

    ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

    Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

    FINANCIAL IMPACT (Budgeted: Yes)

    The budget for interior build-out of the Instructional Services Center is $4,100,000. This item is included in the Community Investment Tax fund. A portion of the interiors work valued at $1,082,334 was transferred from the original construction project. This work will now be completed as part of the build-out project. Any additional credits will be posted to the Land Proceeds fund to be used for other projects.

    EVALUATION

    SUBMITTED BY:

    J. Thomas Blackwell
    General Manager of Construction
    (813) 272-4112
    Cathy L. Valdes
    Chief Facilities Officer
    (813) 272-4004