Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 29, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

ANCILLARY OFFICE BUILDING
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 4 - $655,371.10 CREDIT
APPROVAL OF CHANGE ORDER NO. 5 - $78,900.53 CREDIT

EXECUTIVE SUMMARY

The existing Instructional Services Center had exceeded its useful life and was demolished to allow construction of a two-story 100,000 square foot office building. On March 8, 2005, the Board appointed the design-build firm of R.R. Simmons Construction Corporation to provide design and construction management services for the exterior building shell.

Change Order Nos. 4 and 5 provide credits for the direct purchase of materials by the District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Land Proceeds and Certificates of Participation Series 04C.

Contract Status:
Guaranteed Maximum Price: $8,910,763.00
Change Orders Previously Approved: $1,103,315.38 Credit
Change Order No. 4 Recommended Herein: $655,371.10 Credit
Change Order No. 5 Recommended Herein: $78,900.53 Credit
Revised Guaranteed Maximum Price: $7,073,175.99
Revised Construction Price: $8,805,501.60

Original Completion Date: May 25, 2007
Time Extension Previously Approved: 21 Calendar Days
Revised Completion Date: June 15, 2007

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.15
Hillsborough County Public Schools (Florida) * Mtg.#20070529_244 * Section E Item# 6.15