THONOTOSASSA ELEMENTARY SCHOOL - REMODEL AND RENOVATE
APPROVAL OF CHANGE ORDER NO. 4 - $45,336.99 CREDIT
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Ruyle Masters Hayes + Jennewein Architects. On September 7, 2004, the Board appointed the construction management firm of Heery International, Inc. The scope of work provided for campus-wide replacement of the electrical distribution system, replacement of branch panels and light fixtures at most buildings except 1, 2, and 3 where lamp and ballast replacements will be made, and the addition of walkway lighting, where required. Installation of new fire alarm, intercom, security, and telephone systems throughout the facility was included. Mechanical work included replacement of the obsolete air conditioning systems. Also included was the replacement of exhaust fans and other various upgrades throughout the campus to provide Americans with Disabilities Act (ADA) accessibility. Interior work consisted of the demolition and refinishing of finishes, including casework. Many of these tasks were the result of the demolition required for the mechanical and electrical work. Exterior work included ramp additions at covered walkways to provide ADA accessibility. The scope of work also provided for the addition of windows to Buildings 7, 8, 9, and 11, replacement of window glazing beads at Buildings 1, 2, 3, and 10 and reroofing Building 10. Minor site work consisted of landscaping and correction of site drainage issues.

This change order provides credits for project savings and removal of items from the final punch list. Also included is the final reconciliation of the Direct Purchase Program. The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay 2003-04.
Contract Status:
Guaranteed Maximum Price: $3,051,631.00
Change Orders Previously Approved: $439,566.08 Credit
Change Order Recommended Herein: $45,336.99 Credit
Revised Guaranteed Maximum Price: $2,566,727.93
Payments to Date: $2,514,716.52
Balance Due: $52,011.41
Revised Construction Cost: $3,091,129.78
Original Completion Date: February 28, 2006
Time Extensions Previously Approved: 50 calendar days (Remodel) and 100 calendar days (Site Work)
Revised Completion Dates: April 19, 2006 (Remodel) and June 8, 2006 (Site Work)
Substantial Completion Dates: April 19, 2006 (Remodel) and June 8, 2006 (Site Work)

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.20
Hillsborough County Public Schools (Florida) * Mtg.#20070717_261 * Section E Item# 6.20