Facilities Action Item |
DATE: Tuesday, July 31, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 22, 2005, the Board appointed Holmes Hepner & Associates Architects and Greater Bay Construction Co., Inc. to provide design and construction management services. This facility is a modification of the Pizzo Elementary School design. As of the current boundaries, relief will be provided for Citrus Park, McKitrick, and Schwarzkopf Elementary Schools.
Change Order No. 3 provides a credit for the direct purchase of materials by the District. Change Order No. 4 provides for a new washer and dryer in Room 155, LP (liquid propane) gas tank enclosure, and revision of the stairs, balconies, and railings.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2002 and Classrooms for Kids 2005.
Contract Status:
Guaranteed Maximum Price: $11,927,498.00
Change Orders Previously Approved: $2,780,853.44 Credit
Change Order No. 3 Recommended Herein: $543,842.62 Credit
Change Order No. 4 Recommended Herein: $49,508.55 Extra
Revised Guaranteed Maximum Price: $8,652,310.49
Revised Construction Cost: $11,830,323.88
Contract Completion Date: June 25, 2007
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |