Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, August 7, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

HILLSBOROUGH HIGH SCHOOL
GYMNASIUM REMODEL / ROTC RENOVATION
APPROVAL OF CHANGE ORDER NO. 7 - $24,144.67 EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Wilder Architecture, Inc. On July 11, 2006, the Board awarded the contract to the low bidder, Greater Bay Construction Co., Inc. The scope of work provides for remodel of existing Gymnasium and renovation of a single story wing used for ROTC and classrooms.

This change order provides for two Gymnasium scoreboards not provided by the Pepsi Cola Company as originally planned, changes to the Gymnasium flooring necessitated by unforeseen and concealed conditions, and electrical revisions required by code for football scoreboard and irrigation timer.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2006.

Contract Status:
Contract Sum: $4,018,300.00
Change Orders Previously Approved: $237,972.31 Credit
Change Order Recommended Herein: $24,144.67 Extra
Revised Contract Sum: $3,804,472.36
Revised Construction Cost: $4,395,191.82

Original Completion Date: April 16, 2007
Time Extension Previously Approved: 107 Calendar Days
Revised Completion Date: August 1, 2007

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.08
Hillsborough County Public Schools (Florida) * Mtg.#20070807_263 * Section E Item# 6.08