Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, June 7, 2005
TO: School Board Members
FROM: Earl J. Lennard, Superintendent

SUBJECT / RECOMMENDATIONS

PALM RIVER ELEMENTARY SCHOOL
RENOVATION
APPROVAL OF CHANGE ORDER NO. 6 - $210,494.63 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Rowe Architects, Inc. On March 12, 2002, the Board appointed the construction management firm of Skanska USA Building, Inc.

The scope of work provides for toilet renovations to comply with the Americans with Disabilities Act, re-roofing, electrical service upgrades, new site lighting in parking lots, painting, signage, and replacement of chalkboards with markerboards. It also includes the replacement of HVAC equipment, hardware, ceiling panels, exterior doors, and intercom, telephone, television, and security systems.

This change order provides credits for project savings, return of unused contingency funds, and final reconciliation of the Direct Purchase and Owner Controlled Insurance Programs.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax and Capital Outlay and Debt Service.
Contract Status:
Guaranteed Maximum Price: $3,548,418.00
Change Orders Previously Approved: $316,796.03 Credit
Change Order Recommended Herein: $210,494.63 Credit
Revised Guaranteed Maximum Price: $3,021,127.34
Contract Completion Date: April 30, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
MaryEllen Elia
Chief Facilities Officer
(813) 272-4004
6.15