CHAMBERLAIN HIGH SCHOOL
CULINARY ARTS LAB
APPROVAL OF CHANGE ORDER NO. 1 - $18,138.23 CREDIT / 21 CALENDAR DAY TIME EXTENSION
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of The Architectural Practice, Inc. JBD Construction, Inc. provided construction management services under their continuing services agreement. The scope of work provided for improvement to the teaching facilities at Chamberlain High School's recognized culinary program in cooperation with Outback Restaurant and other suppliers/vendors who assisted with materials, services, and donations.

This change order provides for final reconciliation of the Direct Purchase Program. A time extension is included for completion of added scope to refurbish the toilet rooms.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: 2 Mill.
Contract Status:
Guaranteed Maximum Price: $192,352.00
Change Order Recommended Herein: $18,138.23 Credit
Revised Guaranteed Maximum Price: $174,213.77
Payments to Date: $173,117.00
Balance Due: $1,096.77
Revised Construction Cost: $191,230.96

Original Completion Date: January 2, 2007
Time Extension Recommended Herein: 21 Calendar Days
Revised Completion Date: January 23, 2007
Substantial Completion Date: January 23, 2007